题目内容 (请给出正确答案)
[主观题]

The scope management plan is how the team will prepare the()a document that includes des

criptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.

A.project charter

B.project scope goal

C.project budget

D.project scope statement

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“The scope management plan is h…”相关的问题
第1题
A.project scope statementB.statement of workC.project management planD.project policy

A.project scope statement

B.statement of work

C.project management plan

D.project policy

点击查看答案
第2题
______is primarily concerned with defining and controlling what is and is not included in
the project.

A.Project Time Management

B.Project Cost Management

C.Project Scope management

D.Project Communications Management

点击查看答案
第3题
(75)is primarily concerned with defining and controlling what is and is not included in th
e project.

A.Project Time Management

B.Project Cost Management

C.Project Scope management

D.Project Communications Manageme

点击查看答案
第4题
The inputs of developing project management plan do not include(72). A.project charter B

The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes

点击查看答案
第5题
()确定、记录和管理利益相关者需求和要求的过程,以满足项目目标。

A、Plan Scope Management计划范围管理

B、Collection Requirements收集需求

C、Validate Scope验证范围

D、Control Scope控制范围

点击查看答案
第6题
The Develop Project Management Plan Process includes the actions necessary to define,pre
pare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter

点击查看答案
第7题
● The Develop Project Management Plan Process includes the actions necessary to define, pr
epare, integrate, and coordinate all constituent plans into a (75)

(75)

A. Project Scope Statement

B. Project Management Plan

C. Forecasts

D. Project Charter

点击查看答案
第8题
136 Management reserve is generally intended to be used to: 

A.implement additional unbudgeted scope

B.compensate for inaccurate estimates

C.cover major unforeseen catastrophes

D.cover unforeseen problems in the project

E.All of the above

点击查看答案
第9题
The project () processes include: develop project charter, develop project management

The project () processes include: develop project charter, develop project management plan,direct and manage project work,manage project knowledge,monitor and control project work,perform. integrated change control and close project or phase.

A、integration management

B、scope management

C、schedule management

D、resource management

点击查看答案
第10题
The Develop Project Management Plan Process includes the actions necessary to define, prep
are, integrate, and coordinate all constituent plans into a (75).

A.Project Scope Statement

B.Project Management Plan

C.Forecasts

D.Project Charter

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改