● You are a project manager for a small project. Your project was budgeted for ¥500,000 ov

er a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

(74)

A.Ahead of schedule

B.Behind schedule

C.On schedule

D.Having not enough information provided

查看答案
答案
收藏
如果结果不匹配,请 联系老师 获取答案
您可能会需要:
您的账号:,可能还需要:
您的账号:
发送账号密码至手机
发送
安装优题宝APP,拍照搜题省时又省心!
更多“● You are a project manager fo…”相关的问题
第1题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over
a six-week perio.As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as (74) .

A.Ahead of schedule

B.Behind schedule

C.On schedule

D.Having not enough information provided

点击查看答案
第2题
You'd better______ advice before making a project plan.A.put downB.take inC.turn outD.ask

You'd better______ advice before making a project plan.

A.put down

B.take in

C.turn out

D.ask for

点击查看答案
第3题
Given the estimated decrease in personal profit, what action you should take(46).A.Invoice

Given the estimated decrease in personal profit, what action you should take(46).

A.Invoice for the full $1,000,000 based on the contract.

B.Add tasks to improve the outcome and increase the actual project cost.

C.Inform. the end-user that you can add features to the project in order to use the entire budget.

D.Communicate the projected financial outcome to the project sponsor.

点击查看答案
第4题
As I see it, you should manage-coordinate-the project and () the teams neededto complete it successfully.

A.bring together

B.bring in

C.bring on

点击查看答案
第5题
Daniel: Mr. Taylor, this is the project plan you asked me to make last week.John:Sure. T

Daniel: Mr. Taylor, this is the project plan you asked me to make last week.

John:Sure. That's a quick job. Could you talk me (答案?) the plan roughly?

Daniel:Of course. The plan (答案?) three parts. The first part is the background of the project, the second part is the (答案?), and the third is the expected results.

John:Er…well…I see.

Daniel:Do you have any (答案?) about it?

John:After I read it in detail, I will tell you my opinion.

Daniel:Thanks, and then I will improve it according to your opinion and suggestions.

One day later.

John:I have finished reading your project plan.

Daniel:Is it what you hoped for?

John: Excellent! You seem to have (答案?) all the major points. We've decided to have a meeting. And could you please get ready to give a presentation of your ideas? We have to try our best to (答案?) the board.

A. persuade

B.suggestions

C. covered

D. through

E. includes

F.steps

点击查看答案
第6题
● Your project is behind schedule due to conflict between team members. Having resolved
the conflict, to get the project back on schedule, you should consider __(74)__.

(74)A.crashing the schedule

B.performing resource leveling

C.conducting reverse resource allocation scheduling

D.utilizing the critical chair resources

点击查看答案
第7题
●Your project is behind schedule due to conflict between team members. Having resolved the
conflict, to get the project back on schedule, you should consider(74).

(74) A. crashing the schedule

B. performing resource leveling

C. conducting reverse resource allocation scheduling

D. utilizing the critical chair resources

点击查看答案
第8题
● Your company CEO just sent you an E-mail asking you to make a presentation on your proj
ect, which has been in progress for 10 months, to all identified internal and external stakeholders. He scheduled the presentation for next Monday. You expect more than 50 people to attend. The first step in preparing the presentation is to__(71)__.

(71)A.define the audience

B.determine the objective

C.decide on the general form. of the presentation

D.plan a presentation strategy

点击查看答案
第9题
Your company CEO just sent you an E-mail asking youto make a … on your project , which has
been in progress for 10 months , to all Identified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attend.The first step in preparing the presentation is to ().

A.define the audience

B.determine the objective

C.decide on the general form of the presentation

D.plan a presentation strategy

点击查看答案
第10题
●Ravi, like many project (71) ,had studied the waterfall model of software development as

●Ravi, like many project (71) ,had studied the waterfall model of software development as the primary software life-cycle (72) .He was all set to use it for an upcoming project, his first assignment. However, Ravi found that the waterfall model could not be used because the customer wanted the software delivered in stages, something that implied that the system had to be delivered and built in (73) and not as (74) .The situation in many other projects is not very different. The real world rarely presents a problem in which a standard process, or the process used in a previous project, is the best choice.To be the most suitable, an existing process must be. (75) to the new problem.A development process, even after tailoring, generally cannot handle change requests. To accommodate change requests without losing control of the project, you must supplement the development process with a requirement change management process.

(71) A. customers B.managers C.users D.administrators

(72) A.activity B.procedure C.process D. progress

(73) A.parts B.modules C.software D.a whole

(74) A.parts B.modules C.software D.a whole

(75) A.modified B.used C.suited D. tailored

点击查看答案
退出 登录/注册
发送账号至手机
密码将被重置
获取验证码
发送
温馨提示
该问题答案仅针对搜题卡用户开放,请点击购买搜题卡。
马上购买搜题卡
我已购买搜题卡, 登录账号 继续查看答案
重置密码
确认修改