A.PERT diagram
B.Network Diagram
C.Petri Net
D.Gantt chart
● To determine what causes the majority of quality problems in a process, a very useful tool is the ().()A. cause and effect diagrams B. flow chartC. control chart D. pareto chart
A.gantt chart
B.project histogram
C.milestone chart
D.project flowchart
A__(74)__is a type of bar chart that illustrates a project schedul
A.It illustrates the start and finish dates of the terminal elements and summary elements of a project.
B.Gantt chart
C.project histogram
D.milestone chart
E.project flowchart
A.Levey – Jenning( L-J图)
B.Delta-Chart(差值图)
C.X-S Chart(X-S图)
D.Z Score Chart(Z分数图)